Neosho Ridge Construction Update Mar. 15th to Mar. 21st

We will be working on the following this week throughout the project: ● Road grooming and grading as needed• Foundation work continues in the northwest section of the project• Work continues on the substation at the intersection of 70th Road and Irving Road

ROAD CLOSURE FOR 3/16

ROAD CLOSURE FOR MONDAY, MARCH 16TH (PENDING WEATHER) 85th Road from Hwy 169 to Elk Road will be closed on Monday, March 16th, pending weather.  

ROAD CLOSURE UPDATE 3/13 & 3/14

ROAD CLOSURES FOR TODAY, 3/13 AND 3/14 There will be NO road closures for today, 3/13 and tomorrow, 3/14.

ROAD CLOSURE UPDATE 3/11

ROAD CLOSURES FOR 3/13 & 3/14 100th Road from Gray Road to Harper Road will be closed on Friday, March 13th. 80th Road from Hwy. 169 to Elk Road will be closed on Saturday, March 14th  

Neosho Ridge Construction Update Mar. 8th to Mar. 14th

We will be working on the following this week throughout the project: ● Grooming and grading 80th Road from Irving Road to Hwy. 59● Intersection improvements at 60th Road/Lyon Road, 70th Road/Meade Road and 80th Road/Meade Road• Foundation work continues in the northwest section of the project• Work continues on the substation at the intersection of 70th Road and Irving Road

ROAD CLOSURE UPDATE 3/5

ROAD CLOSURE: Lyon Road from Hwy. 47 to 120th Road will be closed on Saturday, March 7th for most of the day.

Neosho Ridge Construction Update Mar. 1st to Mar. 7th

We will be working on the following this week throughout the project: ● Grooming and maintaining 80th Road from Elk Road to Harper Road• Foundation work continues in the southwest and northwest sections of the project• Work continues on the substation at the intersection of 70th Road and Irving Road

ROAD CLOSURE CORRECTION 2/28

ROAD CLOSURE CORRECTION: The road closure for Sunday, March 1st will take place on Lyon Road from Hwy 47 south to 100th Road. The previous email indicated the road closure would take place on Lyon Road from Hwy 47 north to 120th Road. We apologize for the confusion.

ROAD CLOSURE UPDATE 2/27

ROAD CLOSURES FOR THIS WEEKEND, 2/29 AND 3/1: Saturday, February 29th: 90th Road from Ford Road to Gray RoadEast side of intersection of 80th Road and Meade Road (if time permits). Sunday, March 1st: Lyon Road from Hwy. 47 to 120th Road  

Neosho Ridge Construction Update Feb. 23rd to Feb. 29th

We will be working on the following this week throughout the project: ● Grooming and maintaining Lyon Road from 50th Road to 60th Road and Ness Road from 50th Road to 60th Road• Foundation work continues north of Hwy 47 and in the western portion of the project• Work cancelled for Monday, February 24th due to the weather