Neosho Ridge Construction Update Oct. 11th to Oct. 17th

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work continues on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration continues in the southeast portion of the project ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered north of 80th Road to 100th Road, between Elk and Gray Roads andNorth of Hwy 47 to 130th Road between Harper and Kiowa Roads

FORECASTED HWY 47 ROAD CLOSURE

The road closure that was scheduled to take place next week is tentatively forecasted to take place week 43 (October 19th through October 24th). The closure is slated for 3 hours and will be taking place during daylight hours. The specific location will be between Elk Road and Ford Road. The project staff is aligning directly with KDOT on this activity and will be informing the county 48 hours prior once the specific date and time are established.  

Neosho Ridge Construction Update Oct. 4th to Oct. 10th

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work continues on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered north of 80th Road to 100th Road, between Elk and Gray Roads andNorth of Hwy 47 to 130th Road between Irving and Kiowa Roads  

Neosho Ridge Construction Update Sep. 27th to Oct. 3rd

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work continues on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will be minimal this week Have a great week 😊  

Neosho Ridge Construction Update Sep. 20th to Sep. 26th

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work continues on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will be minimal this week

Neosho Ridge Construction Update Sep. 13th to Sep. 19th

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work has started on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered north of Hwy 47 to 120th Road between Harper and Irving Roads● Additional aggregate will be applied to Jackson Road between 20th and 50th Roads Have a great week 😊  

Neosho Ridge Construction Update Sep. 6th to Sep. 12th

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work has started on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered south of 60th Road between Harper Road and Jackson Road AND 80th Road to 120th Road between Hwy 169 and Irving Road  

Neosho Ridge Construction Update Aug. 30th to Sep. 5th

We will be working on the following this week throughout the project:● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work has started on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered between Hwy. 169 and Ford Road from 70th Road to 120th Road  

Neosho Ridge Construction Update Aug. 23rd to Aug. 29th

We will be working on the following this week throughout the project:● Intersection Improvements: 140th and Kiowa Roads ● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work has started on the O & M building at the northeast section of 70th and Irving Roads ● Site restoration has begun in the southeast portion of the project ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered between Hwy. 169 and Ford Road from 70th Road to 120th Road  

Neosho Ridge Construction Update Aug. 16th to Aug. 22nd

We will be working on the following this week throughout the project:● Intersection Improvements: 140th and Kiowa RoadsHwy. 47 and Elk Road ● Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work has started on the O & M building at the northeast section of 70th and Irving Roads ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered between Hwy. 169 and Ford Road from 60th Road to 120th Road Have a great week 😊