Construction Updates

ROAD CLOSURE TUES. 8/18

100TH ROAD FROM GRAY ROAD TO HARPER ROAD WILL BE CLOSED ON TUESDAY, AUGUST 18TH.

Neosho Ridge Construction Update Aug. 9th to Aug. 15th

We will be working on the following this week throughout the project:● Intersection Improvements: 130th and Irving Roads130th and Jackson Roads ● Foundation backfills continue in the northeast portion of the project • Work continues on the Substation at the northwest intersection of 70th and Irving Roads ● Work has started on the O & M building at the northeast section of 70th and Irving Roads ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered between Elk Road and Gray Road from 60th Road to Hwy 47  

ROAD CLOSURE CANCELLED

ROAD CLOSURE FOR LYON ROAD FROM 60TH ROAD TO 70TH ROAD FOR TODAY AND TOMORROW HAS BEEN CANCELLED.  

ROAD CLOSURE THURS. 8/6 & FRI. 8/7

LYON ROAD FROM 60TH ROAD TO 70TH ROAD WILL BE CLOSED THURSDAY, AUGUST 6TH AND FRIDAY, AUGUST 7TH.

Neosho Ridge Construction Update Aug. 2nd to Aug. 8th

We will be working on the following this week throughout the project:● Intersection Improvements: 130th and Irving Roads130th and Jackson Roads140th and Kiowa Roads ● Foundation backfills continue in the northeast portion of the project • Work continues on the substation at the intersection of 70th Road and Irving Road ● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47 Components will be delivered between 50th and 60th Roads from Ford Road to Gray Road ANDbetween 100th and 120th Roads from Harper Road to Irving Road

Neosho Ridge Construction Update July 26th to August 1st

We will be working on the following this week throughout the project, WEATHER PENDING:● Road Grooming and Grading: Elk Road from 60th Road to 70th RoadKiowa Road from 70th Road to 80th RoadLyon Road from 70th Road to 80th RoadMeade Road from 70th Road to 80th Road ● Intersection Improvements: 120th and Chase Roads150th and Elk Roads ● Foundation backfills continue in the northwest portion of the project • Work continues on the substation at the intersection of 70th Road and Irving Road ● Turbine component deliveries will continue north on Hwy 169, east on Hwy 47 and south on Irving Road. Components will be delivered between 90th Road and 120th Road from Harper Road to Irving Road  

Neosho Ridge Construction Update July 19th to July 25th

We will be working on the following this week throughout the project: ● Road Grooming and Grading: 130th Road from ½ west of Irving Road to Kiowa Road140th Road from Jackson Road to Kiowa RoadJackson Road from 100th Road to Hwy 47Kiowa Road from 130th road to 140th Road ● Intersection Improvements: 80th and Harper Roads80th and Irving Roads ● Foundation backfills continue in the northwest portion of the project • Work continues on the substation at the intersection of 70th Road and Irving Road ● Turbine component deliveries will continue north on Hwy 169, east on Hwy 47 and south on Irving Road. Components will be delivered between 50th Road and 60th Road from Harper Road to Jackson Road and between 90th Road and 100th Road from Hwy 169 to Gray Road  

ROAD CLOSURE WED. 7/22

80TH ROAD FROM IRVING ROAD TO JACKSON ROAD WILL BE CLOSED ON WEDNESDAY, JULY 22ND

ROAD CLOSURE FOR JACKSON ROAD

THE ROAD CLOSURE FOR JACKSON ROAD HAS BEEN EXTENDED FOR ANOTHER DAY. SO, JACKSON ROAD FROM 90TH ROAD TO 100TH ROAD WILL BE CLOSED ON FRIDAY, JULY 17TH.  

ROAD CLOSURE WED. 7/15 & THURS. 7/16

JACKSON ROAD FROM 90TH ROAD TO 100TH ROAD WILL BE CLOSED ON WEDNESDAY, JULY 15TH & THURSDAY, JULY 16TH.