Construction Updates

Neosho Ridge Construction Update Feb. 7th

ROAD CLOSURE UPDATE FOR 02/08/20 ELK ROAD FROM HWY 47 TO 120TH ROAD WILL NOT BE CLOSED ON SATURDAY, FEBRUARY 8TH.

Neosho Ridge Construction Update Feb. 5th

THE FOLLOWING ROADS WILL BE CLOSED ON SATURDAY, FEBRUARY 8TH FROM 8:00 a.m. to 6:00 p.m.: Irving Road from 60th Road to 70th RoadElk Road from Hwy 47 to 120th Road Thank you!

Neosho Ridge Construction Update Feb. 4th

THE FOLLOWING ROAD WILL BE CLOSED ON THURSDAY, FEBRUARY 6TH FROM 8:00 a.m. to 6:00 p.m.: 120TH Road from Elk Road to Ford Road Thank you!

Neosho Ridge Construction Update Feb. 2nd to Feb. 8th

We will be working on the following this week throughout the project: ● Maintaining and grooming 130th Road from Jackson Road to Kiowa Road and 80th Road from Irving Road to Lyon Road• Installing culverts on access roads and delivering rebar to various turbine sites• Foundation work continues north of Hwy 47 and in the western portion of the project

Neosho Ridge Construction Update Jan. 30th

ROAD CLOSURE CORRECTION IN CAPS FOR 02/01: Elk Road from Hwy. 47 to 120th Road120th Road from Elk Road to Ford RoadIrving Road from Hwy. 47 to 130th Road – SHOULD BE IRVING ROAD FROM HWY. 47 TO 90TH ROAD We apologize for any inconvenience.

Neosho Ridge Construction Update Jan. 29th

THE FOLLOWING ROADS WILL BE CLOSED ON SATURDAY, FEBRUARY 1ST from 8:00 a.m. to 6:00 p.m.        Elk Road from Hwy. 47 to 120th Road              120th Road from Elk Road to Ford Road        Irving Road from Hwy. 47 to 130th Road  

Neosho Ridge Construction Update Jan. 26th to Feb. 1st

We will be working on the following this week throughout the project: ● Maintaining and grooming 50th, 60th and 80th Roads as needed• Installing culverts on access roads and delivering rebar to various turbine sites• Placing rock on access roads and working on access road radii• Foundation work continues north of Hwy 47 and in the western portion of the project  

Neosho Ridge Construction Update Jan. 25th

ROAD CLOSURE 80TH ROAD FROM THE INTERSECTION OF ELK ROAD TO THE INTERSECTION OF FORD ROAD WILL BE CLOSED ON SATURDAY, JANUARY 25TH FROM 8:00 A.M. TO 6:00 P.M.  

Neosho Ridge Construction Update Jan. 19th to Jan. 25th

We will be working on the following this week throughout the project: ● Maintaining and grooming Chase Road and Elk Road• Placing rock on Irving Road from Hwy 47 to 70th Road• Delivering rebar to various turbine sites and installing culverts• Foundation work continues north of Hwy 47 and in the western portion of the project  

Neosho Ridge Construction Update Jan. 12th to Jan. 18th

We will be working on the following this week throughout the project: ● Maintaining and grooming 50th Road, Irving Road and other public roads as needed• Installing culverts and placing rock on access roads• Delivering rebar to various turbine sites• Foundation work continues north of Hwy 47 and in the western portion of the project