Construction Updates

Neosho Ridge Construction Update Jan. 5th to Jan. 11th

We will be working on the following this week throughout the project: ● Maintaining and grooming 50th and 60th Roads, along with Elk, Harper, Jackson and Kiowa Roads● Adding aggregate to 140th Road near Highway 169• Installing culverts and placing rock on access roads• Stripping topsoil on foundations• Delivering rebar to various turbine sites  

Neosho Ridge Construction Update Dec. 15th to Dec. 21st

We will be working on the following this week throughout the project: ● Maintaining and grooming Kiowa Road from 90th Road to Hwy 47 and 90th Road from Jackson Road to Kiowa Road• Installing culverts and placing rock on access roads• Stripping topsoil on foundations• Delivering rebar to various turbine sites  

Neosho Ridge Construction Update Dec. 11th

ROAD CLOSURE 80TH ROAD FROM THE INTERSECTION OF MEADE ROAD TO THE INTERSECTION OF NESS ROAD WILL BE CLOSED ON SATURDAY, DECEMBER 14TH FROM 8:00 A.M. TO 6:00 P.M.  

Neosho Ridge Construction Update Dec. 8th to Dec. 14th

We will be working on the following this week throughout the project: ● Maintaining and grooming Irving Road from Hwy 47 to 50th Road and 50th Road from Gray Road to Harper Road • Installing culverts and stabilizing cement• Continuing rock placement on access roads• Stripping topsoil on foundations

Neosho Ridge Construction Update Dec. 4th

ROAD CLOSURE 50TH ROAD BETWEEN MEADE ROAD AND NESS ROAD WILL BE CLOSED ON SATURDAY, DECEMBER 7TH FROM 8:00 A.M. TO 6:00 P.M.

Neosho Ridge Construction Update Dec. 1st to Dec. 7th

We will be working on the following this week throughout the project: ● Maintaining and grooming Elk Road, Harper Road and Irving Road• Stripping topsoil and prepping subgrade on access roads• Installing culverts and continuing rock placement on access roads• Stabilizing cement and delivering rebar to multiple sites  

Neosho Ridge Construction Update Nov. 24th to Nov. 30th

We will be working on the following this week throughout the project: ● Maintaining and grooming Harper Road from 60th Road to 70th Road• Stripping topsoil and prepping subgrade on access roads• Installing culverts and continuing rock placement on access roads• Delivering rebar to multiple sites Happy Thanksgiving!  

Neosho Ridge Construction Update Nov. 17th to Nov. 23rd

We will be working on the following this week throughout the project: ● Maintaining and grooming 60th Road from Kiowa Road to Hwy 59• Stripping topsoil and prepping subgrade on access roads• Installing culverts and continuing rock placement on access roads• Delivering rebar to multiple sites  

Neosho Ridge Construction Update Nov. 10th to Nov. 16th

We will be working on the following this week throughout the project: • Grooming and maintaining 60th Road from Meade Road to Hwy 59• Stripping topsoil and prepping subgrade on access roads• Installing culverts and continuing rock placement on access roads• Stripping topsoil and working on mud mats for foundations• Delivering rebar and stabilizing cement at various sites  

Neosho Ridge Construction Update Nov. 3rd to Nov. 9th

We will be working on the following this week throughout the project: • Adding aggregate to public roads• Stripping topsoil and working on mud mats for foundations• Delivering rebar and stabilizing cement at various sites• Stripping topsoil and prepping subgrade on access roads• Installing culverts and continuing rock placement on access roads