We will be working on the following this week throughout the project:
● Road grooming and grading: 80th Road from Harper Road to Kiowa Road
Jackson Road from 80th Road to Hwy 47
● Intersection improvements: 80th and Elk Roads
• Foundation backfills continue throughout the project
• Work continues on the substation at the intersection of 70th Road and Irving Road