Neosho Ridge Construction Update Apr. 26th to May 2nd

We will be working on the following this week throughout the project:

● Road grooming and grading: 80th Road from Harper Road to Kiowa Road
   Jackson Road from 80th Road to Hwy 47

● Intersection improvements: 80th and Elk Roads

• Foundation backfills continue throughout the project

• Work continues on the substation at the intersection of 70th Road and Irving Road