We will be working on the following this week throughout the project:
● Work continues on the Substation at the northwest intersection of 70th and Irving Roads
● Work has started on the O & M building at the northeast section of 70th and Irving Roads
● Site restoration has begun in the southeast portion of the project
● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47
Components will be delivered between Hwy. 169 and Ford Road from 70th Road to 120th Road