We will be working on the following this week throughout the project:
● Intersection Improvements: 130th and Irving Roads
130th and Jackson Roads
● Foundation backfills continue in the northeast portion of the project
• Work continues on the Substation at the northwest intersection of 70th and Irving Roads
● Work has started on the O & M building at the northeast section of 70th and Irving Roads
● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47
Components will be delivered between Elk Road and Gray Road from 60th Road to Hwy 47