We will be working on the following this week throughout the project:
- Work continues on the Substation at the northwest intersection of 70th and Irving Roads
- Work continues on the O & M building at the northeast section of 70th and Irving Roads
- Site restoration is ongoing in the southeast and southwest portions of the project
- Delivery of turbine components is complete
- All towers south of Hwy. 47 have been erected
Have a very Merry Christmas!