Neosho Ridge Construction Update Dec. 6th to Dec. 12th

We will be working on the following this week throughout the project:

   

  • Work continues on the Substation at the northwest intersection of 70th  and Irving Roads

 

  • Work continues on the O & M building at the northeast section of 70th and Irving Roads

 

  •  Site restoration is ongoing in the southeast and southwest portions of the project

 

  •  DELIVERY OF TURBINE COMPONENTS IS COMPLETE