We will be working on the following this week throughout the project:
- The Substation at the northwest intersection of 70th and Irving Roads is complete
- The O & M building at the northeast section of 70th and Irving Roads is near completion
- Site restoration is ongoing south of Hwy. 47
- All towers south of Hwy. 47 have been erected
- Tower erection continues north of Hwy. 47 and west of Hwy. 169