Neosho Ridge Construction Update Jan. 26th to Feb. 1st

We will be working on the following this week throughout the project:

● Maintaining and grooming 50th, 60th and 80th Roads as needed
• Installing culverts on access roads and delivering rebar to various turbine sites
• Placing rock on access roads and working on access road radii
• Foundation work continues north of Hwy 47 and in the western portion of the project