We will be working on the following this week throughout the project:
- The Substation at the northwest intersection of 70th and Irving Roads is complete
- The O & M building at the northeast section of 70th and Irving Roads is near completion
- Site restoration is ongoing south of Hwy. 47
- All tower erection is complete.
- Demobilization of cranes and equipment has begun