Neosho Ridge Construction Update July 5th to July 11th

We will be working on the following this week throughout the project:

● Road Grooming and Grading: 120th Road from Chase Road to Hwy 169
120th Road from Elk Road to Ford Road
Chase Road from 120th Road to 140th Road
Elk Road from Hwy 47 to 120th Road

● Intersection Improvements: 70th and Elk Roads
80th and Irving Roads
90th and Elk Roads
95th and Elk Roads
120th Road and Hwy 169

● Foundation backfills continue north of Hwy 47 and in the northwest portion of the project

• Work continues on the substation at the intersection of 70th Road and Irving Road

● Turbine component deliveries will continue north on Hwy 169, east on Hwy 47 and south on Irving Road.
Components will be delivered south of Hwy 47 to 50th Road and east of Irving Road to Hwy 59.