We will be working on the following this week throughout the project:
● Road grooming and grading: 60th Road from Kiowa Road to Hwy 59
100th Road from Ford Road to Jackson Road
● Intersection improvements: 60th and Meade Roads
70th and Meade Roads
80th and Harper Roads
80th and Lyon Roads
80th and Meade Roads
• Foundation work continues in the northwest section of the project
• Work continues on the substation at the intersection of 70th Road and Irving Road