Neosho Ridge Construction Update May 31st to June 6th

We will be working on the following this week throughout the project:

● Road grooming and grading: 100th Road from Ford Road to Jackson Road
Kiowa Road from 90th Road to Hwy 47

● Intersection improvements: 60th and Gray Roads

● Foundation backfills continue throughout the project

• Work continues on the substation at the intersection of 70th Road and Irving Road

● Turbine component deliveries continue in the southeast portion of the project