Neosho Ridge Construction Update May 3rd to May 9th

We will be working on the following this week throughout the project:

● Road grooming and grading: 60th Road from Gray Road to Irving Road
Irving Road from 50th Road to 60th Road


● Foundation backfills continue throughout the project

• Work continues on the substation at the intersection of 70th Road and Irving Road