We will be working on the following this week throughout the project:
● Road grooming and grading: 60th Road from Gray Road to Irving Road
Irving Road from 50th Road to 60th Road
● Foundation backfills continue throughout the project
• Work continues on the substation at the intersection of 70th Road and Irving Road