Neosho Ridge Construction Update Nov. 17th to Nov. 23rd

We will be working on the following this week throughout the project:

● Maintaining and grooming 60th Road from Kiowa Road to Hwy 59
• Stripping topsoil and prepping subgrade on access roads
• Installing culverts and continuing rock placement on access roads
• Delivering rebar to multiple sites