Neosho Ridge Construction Update Oct. 11th to Oct. 17th

We will be working on the following this week throughout the project:

● Work continues on the Substation at the northwest intersection of 70th and Irving Roads

● Work continues on the O & M building at the northeast section of 70th and Irving Roads

● Site restoration continues in the southeast portion of the project

● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47
Components will be delivered north of 80th Road to 100th Road, between Elk and Gray Roads and
North of Hwy 47 to 130th Road between Harper and Kiowa Roads