Neosho Ridge Construction Update Oct. 13th to Oct. 19th

The following will be performed in the southern most part and central part of the project:

• Off loading rebar at various sites
• Moving cranes site to site, slow wide loads
• Continuing access road rock placement south of Highway 47
• Working on mud mats at various sites
• Cement stabilization at multiple sites
• Road maintenance on all public roads south of Highway 47