Neosho Ridge Construction Update Oct. 25th to Oct. 31st

We will be working on the following this week throughout the project WEATHER PENDING:

● Work continues on the Substation at the northwest intersection of 70th and Irving Roads

● Work continues on the O & M building at the northeast section of 70th and Irving Roads

● Site restoration continues in the southeast portion of the project

● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47.
Components will be delivered north of 120th Road between Jackson and Lyon Roads and
North of 70th Road to 80th Road between Gray and Irving Roads