We will be working on the following this week throughout the project:
• Stripping topsoil and prepping subgrade on access roads
• Installing culverts and continuing rock placement on access roads
• Stripping topsoil and working on mud mats for foundations
• Delivering rebar to multiple sites
• Stabilizing cement at various sites