Neosho Ridge Construction Update Sep. 13th to Sep. 19th

We will be working on the following this week throughout the project:

● Work continues on the Substation at the northwest intersection of 70th and Irving Roads

● Work has started on the O & M building at the northeast section of 70th and Irving Roads

● Site restoration has begun in the southeast portion of the project

● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47
Components will be delivered north of Hwy 47 to 120th Road between Harper and Irving Roads

● Additional aggregate will be applied to Jackson Road between 20th and 50th Roads

Have a great week 😊