Neosho Ridge Construction Update Sep. 25th to Sep. 28th

For the remainder of the week, we will be working on the following:

Grooming and maintaining public roads: 80th Road from Harper Road to Lyon Road; Elk Road from 60th Road to 80th Road; 60th Road from Elk Road to Harper Road; 140th Road from Chase Road to Highway 169

Continue stripping topsoil and prepping access roads in the south central and south west areas of the project