Neosho Ridge Construction Update Sep. 27th to Oct. 3rd

We will be working on the following this week throughout the project:

● Work continues on the Substation at the northwest intersection of 70th and Irving Roads

● Work continues on the O & M building at the northeast section of 70th and Irving Roads

● Site restoration has begun in the southeast portion of the project

● Turbine component deliveries will be minimal this week


Have a great week 😊