Neosho Ridge Construction Update Sep. 6th to Sep. 12th

We will be working on the following this week throughout the project:

● Work continues on the Substation at the northwest intersection of 70th and Irving Roads

● Work has started on the O & M building at the northeast section of 70th and Irving Roads

● Site restoration has begun in the southeast portion of the project

● Turbine component deliveries will continue north on Hwy 169 and east on Hwy 47
Components will be delivered south of 60th Road between Harper Road and Jackson Road AND 80th Road to 120th Road between Hwy 169 and Irving Road